The City of Gillette, Purchasing Division, opened bids for the project at the City Warehouse on Tuesday, January 21, 2020 at 10:00 A.M.
The following table summarizes the bids received and the Engineer’s Estimate.
Bidder
|
Base Bid
|
Alternate A
|
Alternate B
|
Total Bid
|
Hardrives Construction, Inc.
|
$ 316,616.50
|
$ 70,074.60
|
$ 13,230.00
|
$ 399,754.10
|
Simon Contractors
|
$ 392,329.50
|
$ 111,400.00
|
$ 23,100.00
|
$ 526,829.50
|
Croell, Inc.
|
$ 513,788.50
|
$ 128,288.00
|
$ 33,600.00
|
$ 675,676.50
|
Knife River
|
$ 457,812.50
|
$ 198,691.20
|
$ 45,297.00
|
$ 701,800.70
|
Engineer’s Estimate
|
$ 273,572.00
|
$ 91,452.00
|
$ 8,820.00
|
$ 373,844.00
|
BID IRREGULARITIES: No bid irregularities were found. All four bids were received on time, three (3) bids included a “Certificate of Residency” and the 5% Wyoming Preference was applied to one bid, Hardrives Construction, Inc. of Billings, MT.
CONSTRUCTION ESTIMATE: The total construction cost for this project was estimated at $373,844.00 and was prepared by the City of Gillette Engineering Division. The low bid from Hardrives Construction, Inc. was $399,754.10, with 5% added by the Wyoming Preference Act their bid totaled $419,752.31, which was still less than the second lowest bid of $526,829.50. The Hardrives Construction, Inc. bid was approximately 7% higher than the Engineer’s Estimate. The difference will be made up from savings on previous projects.
Budget: The funding for this project has been allocated from the 1% Optional Sales Tax.
|