Bid Opening
On Tuesday February 12, 2020, bids were opened and read aloud by the City of Gillette Purchasing Division. Three bids were received.
Mountain Peak Builders $98,675.10
Powder River Construction $110,219.37
S & S Builders $127,395.00
Engineer's Estimate $127,395.00
No errors were found in the bids. Mountain Peak Builders was the lowest qualified bid.
Mountain Peak Builders has indicated they are comfortable with their bid. Mountain Peak Builders successfully completed last years Alley Pavement Management Project within the time allowed. They have the necessary equipment and staff to complete this project.
The funding for this project has been allocated from the Optional 1% Account 201-10-05-419-40-44331. |