Approval Sheet

CITY OF GILLETTE
201 E. 5th Street
Phone (307)686-5200
CITY OF GILLETTE


www.gillettewy.gov

 
DATE: 3/3/2020 7:00:00 PM
SUBJECT:
Council Consideration for the Acceptance of Public Improvements for the Gillette Madison Pipeline Project, Contract 2b, Installed by Hot Iron, Inc., in the Amount of $7,228,655.41.
BACKGROUND:
This project consisted of the installation of approximately 6.75 miles of 14-inch raw waterline, 0.59 miles of 30-inch raw waterline, two pre-manufactured well houses, one pre-manufactured control valve building, two permanent pumping equipment installations, and all associated appurtenances necessary to connect wells M-11 and M-12 to the transmission line at the Pine Ridge Disinfection Facility. This project occurred primarily in the State section located to the north of the Pine Ridge Disinfection Facility in Crook County.
ACTUAL COST VS. BUDGET:

The original contract amount for this project was $6,426,027.33.  There were eleven change orders for a net added cost to the project of $802,628.08.  Below is a summary of these change orders:

Change Order Description Contract Time Amount
01 Electrical Modifications +3 Days $ 26,247.45
02 Addition of Remote Racking Breaker Device +25 Days $ 10,720.15
03 Pitless Unit Modifications Removal Milestone Date/+25 Days $ 87,284.00
04 Enhanced Bond Logging per WDEQ Investigation +25 Days $250,625.50
05 Additional Well Bore Cleaning for Bond Logging M11 N/A $ 71,151.25
06 Additional Storage and Disposal of Water from M12 N/A $ 21,204.00
07 Installation of Flushing Interconnect between 30" Waterlines N/A $ 94,522.00
08 Additional Storage and Disposal of Water from M12 N/A $ 24,294.00
09 Additional Work to Comply with Discharge Permit for Flushing +252 Days $173,428.78
10 Replacement of Phase Shift Transformer +68 Days $ 46,015.75
11 Phase Shift Transformer Salvage, Warranty Modifications, Final Quantity Adjustments N/A $ (2,864.80)

Hot Iron finished the project within the allotted contract time; therefore, no liquidated damages were deducted from payments.

Budget Account No.  301-70-72-441-70-47411

Project No. 07EN58
SUGGESTED MOTION:
I Move for Approval for the Acceptance of Public Improvements for the Gillette Madison Pipeline Project, Contract 2b, Installed by Hot Iron, Inc., in the Amount of $7,228,655.41.
STAFF REFERENCE:
MAP - Michael H. Cole, P.E., Utilities Director
ATTACHMENTS:
Click to download
Project Exhibit
Affidavit on Behalf of Contractor
Certificate of Final Completion
Warranty Agreement
Engineer's Recommendation