Approval Sheet

CITY OF GILLETTE
201 E. 5th Street
Phone (307)686-5200
CITY OF GILLETTE


www.gillettewy.gov

 
DATE: 4/21/2020 7:00:00 PM
SUBJECT:
Council Consideration of Amendment No. 8 for the Project Agreement for the Gillette Madison Pipeline Project to Extend the Project Completion Date to July 1, 2022, with the State of Wyoming Water Development Commission (WWDC).
BACKGROUND:
The attached Amendment is necessary for the State of Wyoming Water Development Commission to continue to encumber the grant funding associated with the Gillette Madison Pipeline Project to allow City enough time to complete the project.
Staff recommends approval of this Amendment.
ACTUAL COST VS. BUDGET:

The proposed action does not affect the project budget. The proposed action extends the time frame in which we can use the WWDC grant funds.

Project No. 07EN58
Budget Account No. 301-70-72-441-70-47411
SUGGESTED MOTION:
I Move to Approve Amendment No. 8 for the Project Agreement for the Gillette Madison Pipeline Project to Extend the Project Completion Date to July 1, 2022, with the State of Wyoming Water Development Commission (WWDC).
STAFF REFERENCE:
Michael H. Cole, P.E., Utilities Director
ATTACHMENTS:
Click to download
Project Agreement Amendment