The City of Gillette, Purchasing Division, opened bids for this project at the City Warehouse on Wednesday, February 26, 2020 at 2:30 P.M.
The following table summarizes the one bid received and the Engineer's Estimate.
BIDDER
|
BASE BID
|
ADD ALTERNATE A
|
ADD ALTERNATE B
|
DRM, Inc.
|
$5,079,783.82
|
$482,589.72
|
$108,264.96
|
Engineer’s Estimate (HDR)
|
$3,582,760.00
|
$308,855.00
|
$70,221.00
|
BID IRREGULARITIES
The bid is $2,120,638.50 higher than the available funding. No arithmetic errors were found in the one bid. In general, bid unit prices were higher for all parts of the work than historic prices. The higher than normal prices were a result of lack of competition, high availability of other work in the area and location of this project (Lakeway Road).
Based on the above evaluation, HDR recommends the City of Gillette not award the project to DRM, Inc. for $5,670,638.50.
CONSTRUCTION ESTIMATE
The total construction cost for this project was estimated at $3,961,836.00.
BUDGET
The funding for this project has been allocated from the 1% Optional Sales Tax Account 201-10-05-419-70-47420 in the amount of $3,550,000.00. If this project is awarded we would be $2,120,638.50 over budget.
CONTRACTORS REVIEW
DRM, Inc. has no apparent problems with their bid.
Bid Tabulation is attached. |