DATE:
|
5/19/2020 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for the Wastewater Treatment Plant Ultra Violet Disinfection Building Addition Project, Installed by Van Ewing Construction, Inc., in the Amount of $489,221.52. |
BACKGROUND: |
This project was a two room addition to the Ultra Violet (UV) Disinfection Building to relocate electrical equipment associated with the UV Disinfection system, installation of a new air handler unit, reconfiguration of existing air handler duct work, installation of a new air conditioner for the new electrical equipment room. |
ACTUAL COST VS. BUDGET: |
The original contract amount for this project was $485,000.00. There were two change orders for a net increased cost to the project of $4,221.52 (0.9% increase). Below is a summary of these change orders:
Change Order |
Description |
Contract Time |
Change Order Amount |
01 |
Slope Paving |
0 |
$ 3,135.32 |
02 |
Condensate Drain |
0 |
$ 1,086.20 |
Budget Account No. 505-70-75-443-70-47510
|
SUGGESTED MOTION: |
I Move for Approval for the Acceptance of Public Improvements for the Wastewater Treatment Plant Ultra Violet Disinfection Building Addition Project, Installed by Van Ewing Construction, Inc., in the Amount of $489,221.52. |
STAFF REFERENCE: |
VIDEO - Michael H. Cole, P.E., Utilities Director |
|
|