|
DATE:
|
4/15/2013 7:00:00 PM |
SUBJECT: |
Council Consideration of a Permanent Waterline and General Utility Easement and Temporary Construction Easement for the Gillette Madison Pipeline Project with Jesse and Christina Kirschenmann, c/o Campbell County Abstract Company, in the Amount of $17,313.00. |
BACKGROUND: |
Attached is a copy of the easement documents with Jesse and Christina Kirschenmann, c/o Campbell County Abstract Company. This easement segment is necessary for our next pipeline construction contract between Wyodak and Moorcroft along State Highway 51.
Easements in excess of $5,000 for the Gillette Madison Pipeline Project are being considered individually by the Council on the Consent Agenda. Easements less than $5,000 are considered by the Council on the Claims List.
Staff recommends approval of this easement payment. |
ACTUAL COST VS. BUDGET: |
Payment for this easement is eligible for reimbursement from the Wyoming Water Development Commission through our 67% grant and 33% loan we have with them for the Gillette Madison Pipeline Project.
Budget Account No. 301-4530-441-7411 Project No. 07EN58 |
SUGGESTED MOTION: |
I move to approve payment for a Permanent Waterline and General Utility Easement and Temporary Construction Easement for the Gillette Madison Pipeline Project with Jesse and Christina Kirschenmann, c/o Campbell County Abstract Company, in the amount of $17,313.00. |
STAFF REFERENCE: |
Kendall Glover, Utilities Director |
|
|