DATE:
|
6/17/2013 7:00:00 PM |
SUBJECT: |
Council Consideration of a Permanent Water Line and General Utility Easement and a Temporary Construction Easement for the Gillette Regional Water Supply Project - Phase I District Extensions with Mark D. & Jerri D. Hettinger; Mark D. & Jerri D. Hettinger Revocable Trust; and the Mark D. Hettinger Revocable Trust c/o Campbell County Abstract Co. in the Amount of $11,964.00. |
BACKGROUND: |
Attached is a copy of the easement documents with Mark D. & Jerri D. Hettinger c/o Campbell County Abstract Co. This easement is necessary to construct the Priority I Regional Water District Extension Project in the Force Road Area.
Easements in excess of $5,000 for this project are being considered individually by the Council on the Consent Agenda. Easements less than $5,000 are considered by the Council on the Claims List.
Staff recommends approval of this easement payment. |
ACTUAL COST VS. BUDGET: |
Payment for this easement is eligible for reimbursement from the Wyoming Water Development Commission through our 67% grant we have with them for the Gillette Regional Water Supply - Phase I District Extensions Project. The other 33% will come from the District Extension portion of the Capital Facilities Tax revenue.
Budget Account No. 301-4530-441-7421 Project No. 12UT05 |
SUGGESTED MOTION: |
I Move to Approve Payment of a Permanent Water Line and General Utility Easement and a Temporary Construction Easement for the Gillette Regional Water Supply Project - Phase I District Extensions with Mark D. & Jerri D. Hettinger; Mark D. & Jerri D. Hettinger Revocable Trust; and the Mark D. Hettinger Revocable Trust c/o Campbell County Abstract Co. in the Amount of $11,964.00. |
STAFF REFERENCE: |
Kendall Glover, Utilities Director |
|
|