DATE:
|
6/17/2013 7:00:00 PM |
SUBJECT: |
Council Consideration of a Permanent Water Line and General Utility Easement and a Temporary Construction Easement for the Gillette Madison Pipeline Project with James G. and Lynette Frost c/o Campbell County Abstract Company in the Amount of $10,000.00. |
BACKGROUND: |
Attached is a copy of the easement documents with James G. and Lynnette Frost c/o Campbell County Abstract Company. This easement is necessary to construct our next pipeline segment between Wyodak and Moorcroft along State Highway 51 near Rozet.
Easements in excess of $5,000 for the Gillette Madison Pipeline Project are being considered individually by the Council on the Consent Agenda. Easements less than $5,000 are considered by the Council on the Claims List.
Staff recommends approval of this easement payment. |
ACTUAL COST VS. BUDGET: |
Payment for this easement is eligible for reimbursement from the Wyoming Water Development Commission through our 67% grant and 33% loan we have with them for the Gillette Madison Pipeline Project.
Budget Account No. 301-4530-441-7411 Project No. 07EN58 |
SUGGESTED MOTION: |
I Move to Approve Payment of a Permanent Water Line and General Utility Easement and a Temporary Construction Easement for the Gillette Madison Pipeline Project with James G. and Lynette Frost c/o Campbell County Abstract Company in the amount of $10,000.00. |
STAFF REFERENCE: |
Kendall Glover, Utilities Director |
|
|