DATE:
|
6/17/2013 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for the Fox Park - Arley Acres Drainage Improvements Project, Installed by DRM, Inc., in the Amount of $371,225.00. |
BACKGROUND: |
This project consisted of regrading the east borrow pit of Anvil Lane to Forge Court, regrading of the north borrow pit of Forge Court from Anvil Lane to the east end of Forge Court, installation of 1600 lineal feet of storm sewer from the east end of Forge Court to the end of Gordon Street, and through the Fox Park park area. The project also included drainage improvements to Smithie Court including a concrete lined channel.
The project was completed within the allotted construction days, including a scheduled winter shutdown.
|
ACTUAL COST VS. BUDGET: |
This project was awarded in the amount of $382,709.00. There were two (2) change orders resulting in a net decrease to the contract in the amount of $11,484.00. The final contract amount was $371,225.00.
The project was funded from the 1% Optional Sales Tax Account #201-1011-419.74-05.
|
SUGGESTED MOTION: |
I move for Approval of the Acceptance of Public Improvements for the Fox Park - Arley Acres Drainage Improvements Project, Installed by DRM, Inc., in the Amount of $371,225.00.
|
STAFF REFERENCE: |
VIDEO Dustin Hamilton, P.E., Director of Engineering and Development Services |
|
|