DATE:
|
9/16/2013 7:00:00 PM |
SUBJECT: |
Council Consideration of a Warranty Deed, Permanent Water Line & General Utility Easement, and Temporary Construction Easement for the Gillette Regional Water Supply Project (Phase I District Extensions) with the Roger Wayne Oedekoven Trust, c/o Campbell County Abstract Company, in the Amount of $15,471.00. |
BACKGROUND: |
Attached is a copy of the easement documents with the Roger Wayne Oedekoven Trust, c/o Campbell County Abstract Company. This easement is necessary to construct the Priority I Regional Water District Extension Project in the Force Road Area.
Easements in excess of $5,000 for this project are being considered individually by the Council on the Consent Agenda. Easements less than $5,000 are considered by the Council on the Claims List.
Staff recommends approval of this easement payment. |
ACTUAL COST VS. BUDGET: |
Payment for this warranty deed and easement is eligible for reimbursement from the Wyoming Water Development Commission through our 67% grant we have with them for the Gillette Regional Water Supply - Phase I District Extensions Project.
The other 33% will come from the District Extension portion of the Capital Facilities Tax revenue.
Budget Account No. 301-70-72-441-70-47414 Project No. 12UT05 |
SUGGESTED MOTION: |
I Move to Approve a Warranty Deed, Permanent Water Line & General Utility Easement, and Temporary Construction Easement for the Gillette Regional Water Supply Project (Phase I District Extensions) with the Roger Wayne Oedekoven Trust, c/o Campbell County Abstract Company, in the Amount of $15,471.00. |
STAFF REFERENCE: |
Kendall Glover, Utilities Director |
|
|