DATE:
|
10/7/2013 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for the Heritage Village Park Irrigation Project, Installed by G & G Landscape Inc., in the Amount of $78,964.22. |
BACKGROUND: |
This project is associated with the replacement of the Heritage Village Park irrigation system. The project consists of the design and installation of a new irrigation system. |
ACTUAL COST VS. BUDGET: |
Funding for this project will be paid for from the 1% Optional Sales Tax Fund (Account #201-1011-419-73-11 (Park Improvements). The original contract price was $76,500.00. There was one change order for $2,464.22, to remedy an unforeseen problem with the backflow preventer and to adapt the new mainline for additional zone expansion to water newly planted trees. The final contract price was $78,964.22. The cost for the design of this project was $20,086.44. Construction management, done by FourFront Design, was $6,579.79.
Total project cost including design, construction and construction management was $105,630.45. Originally, the budget for this project was $225,000.00. Landscape Architect's estimate was $184,141.50. |
SUGGESTED MOTION: |
I move for Approval for the Acceptance of Public Improvements for the Heritage Village Park Irrigation Project installed by G & G Landscaping, Inc., in the amount of $78,964.22. |
STAFF REFERENCE: |
Sawley Wilde, Public Works Director |
|
|