Council Consideration for the Acceptance of Public Improvements for 2011 Water Main Replacement Project, Installed by DRM, Inc., in the Amount of $770,765.79. |
BACKGROUND: |
This project replaced 909 LF of 12" Ductile Iron water main and 1209 LF of 12" Cast Iron water main with 12" PVC water main in Veterans Drive from 8th Street to I-90. Also included with this water main replacement was installation of 142 LF of Storm Sewer, 1934 LF of Curb and Gutter, and 5186 SY of Asphalt Pavement.
|
ACTUAL COST VS. BUDGET: |
There were four (4) change orders associated with this project that decreased the contract by $142,317.31 from the original contract amount of $913,083.10.
Change Order | Description | Contract Days Added | Force Account Amount | Contract Amount | 1 | Additional water and sewer stubs for the future Pioneer Manor site on the south end of property | 2 | $7,110.00 | $0.00 | 2 | Additional water and sewer stubs for future Pioneer Manor site on the north end of property, connect 1” water service at Sta 13+25, repair storm sewer at Circle Drive | 2 | $26,324.58 | $0.00 | 3 | Modify storm sewer system to accommodate utility conflicts, modify storm inlets for elevation change, jackhammer concrete at south connection point, repair irrigation at Circle Drive, 12th Street re-bore due to concrete abutment conflict | 0 | $9,066.19 | $0.00 | 4 | Install 2” water service to irrigation meter pit, irrigation repairs, final quantity adjustment | 0 | $0.00 | -$142,317.31 | | Total | 4 | $42,500.77 | -$142,317.31 |
|
SUGGESTED MOTION: |
I Move for the Approval of the Acceptance of Public Improvements for 2011 Water Main Replacement Project, Installed by DRM, Inc. in the Amount of $770,765.79.
|