DATE:
|
10/7/2013 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for the City West Parking Lot Landscaping Project, Installed by G & G Landscape, Inc., in the Amount of $73,734.48. |
BACKGROUND: |
This project consisted of the installation of new landscaping features in and around the new parking lot located at City West. This new landscaping includes trees, shrubs, rock mulch, water conservative sod and a centrally controlled irrigation system which will provide water separately to all trees, shrubs and grass areas.
The original construction time was 25 working days to substantial completion and 35 working days to final completion. There were 3 days added to the contract for changes in the work. G & G Landscape, Inc. completed the project within the allotted time.
|
ACTUAL COST VS. BUDGET: |
The original contract price was in the amount of $72,145.00.
There was one (1) change order on the project for final quantity adjustments, resulting in a net increase to the project of $1,589.48. The final contract amount was $73,734.48.
This project was funded from the Special Projects Building Account #001-10-04-419-70-47210.
|
SUGGESTED MOTION: |
I move for Approval of the Acceptance of Public Improvements for the City West Parking Lot Landscaping Project, Installed by G & G Landscape, Inc., in the Amount of $73,734.48.
|
STAFF REFERENCE: |
VIDEO
Dustin Hamilton, P.E., Development Services Director |
|
|