DATE:
|
10/21/2013 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for Water Tank Rehabilitation (Z1-R1) - Painting Project, Installed by Western Industrial, Inc., in the Amount of $523,664.79. |
BACKGROUND: |
This 1% Optional Sales Tax project consisted of painting the two million gallon steel water storage tank (Z1-R1 Cemetery Tank). The work included removal of interior and exterior paint and re-painting the interior and exterior of the tank.
|
ACTUAL COST VS. BUDGET: |
There was only one (1) change order associated with this project that decreased the contract by $60,991.21 from the original contract amount of $584,656.00.
Change Order | Description | Contract Days Added | Force Account Amount | Contract Amount | 1 | Additional Weld Inspection Services, Resolution of Painted Fence, and Reconciliation of Final Quantities | 0 | $0.00 | -$60,991.21 | | Total | 0 | $0.00 | -$60,991.21 |
|
SUGGESTED MOTION: |
I Move for the Approval of the Acceptance of Public Improvements for the Water Tank Rehabilitation (Z1-R1)-Painting Project, Installed by Western Industrial, Inc. in the Amount of $523,664.79.
|
STAFF REFERENCE: |
PHOTO/VIDEO
Kendall Glover, Utilities Director |
|
|