|
DATE:
|
11/19/2013 7:00:00 PM |
SUBJECT: |
Council Consideration of a Permanent Waterline and General Utility Easement and a Temporary Construction Easement for the Gillette Madison Pipeline Project with the Francis and Elvira Thar Revocable Living Trust c/o Campbell County Abstract Company in the Amount of $5,078.00. |
BACKGROUND: |
Attached is a copy of the easement documents with the Thar Revocable Living Trust c/o Campbell County Abstract Comapny. This easement segment is necessary for our next pipeline construction contract between Wyodak and Moorcroft along State Highway 51. Easements in excess of $5,000 for the Gillette Madison Pipeline Project are being considered individually by the Council on the Consent Agenda. Easements less than $5,000 are considered by the Council on the Claims List. Staff recommends approval of this easement payment. |
ACTUAL COST VS. BUDGET: |
Payment for this easement is eligible for reimbursement from the Wyoming Water Development Commission through our 67% grant and 33% loan we have with them for the Gillette Madison Pipeline Project.
Budget Account No. 301-70-72-441-70-47411 Project No. 07EN58 |
SUGGESTED MOTION: |
I Move to Approve Payment of a Permanent Waterline and General Utility Easement and a Temporary Construction Easement for the Gillette Madison Pipeline Project with the Francis and Elvira Thar Revocable Living Trust c/o Campbell County Abstract Company in the Amount of $5,078.00. |
STAFF REFERENCE: |
Kendall Glover, Utilities Director |
|
|