The Antelope Valley Business Park (AVBP) is responsible for all WWDC non-eligible costs associated with this project. DOWL HKM's estimated design cost of $35,500.00 is described further within the attached amendment.
Of this total amount, $32,000.00 is DOWL HKM's estimate to design the additional improvements as identified within the attached amendment. This $32,000.00 will be paid by the City and reimbursed by the AVBP per the terms and conditions of the separate AVBP Water Service Agreement. Attached is a copy of a check provided by the AVBP for the cost of the additional engineering design services. This $32,000.00 amount is not eligible for WWDC reimbursement.
The remaining $3,500.00 is additional costs necessary to revise easement exhibits and legal descriptions during staff negotiations with affected landowners. Sixty-seven percent (67%) of the $3,500.00 cost is eligible for reimbursement by the WWDC through our Project (grant funding) Agreement we have with them.
Project No. 12UT05 Budget Account No. 301-70-72-441-70-47414 |