DATE:
|
3/4/2014 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for the Donkey Creek Substation Foundation/Transformer Pad Project as Completed by Michael's Construction, Inc., in the Amount of $54,523.00. |
BACKGROUND: |
The scope of this project covers the installation of the concrete foundations and transformer oil containment for the new Donkey Creek Substation.
|
ACTUAL COST VS. BUDGET: |
The engineering estimate for this project was $70,000.00. This project was completed at the original contract amount of $54,523.00
|
SUGGESTED MOTION: |
I Move for Approval of the Acceptance of Public Improvements for the Donkey Creek Substation Foundation/Transformer Pad Project, Installed by Michael's Construction, Inc., in the Amount of $54,523.00.
|
STAFF REFERENCE: |
Kendall Glover, Utilities Director |
|
|