The City of Gillette, Purchasing Division, opened bids for this project at the City Warehouse on Wednesday, April 23, 2014 at 11:00 am.
The results of the bid as follows:
Bidder
|
Base Bid
|
Alternate 2
|
Alternate 3
|
Unit Price 1
|
Total $
|
Michaels Construction
|
$121,475.00
|
$3,822.00
|
$15,225.00
|
$4.75/SF
|
$140,522.00
|
Hladky Construction
|
$149,168.00
|
$10,558.00
|
$20,708.00
|
$145.27/32 SF
$4.54/SF
|
$180,434,00
|
S &S Builders
|
$149,159.00
|
$8,826.00
|
$15,431.00
|
$1.84/SF $59.00
|
$173,416.00
|
Bid Irregularities:
There were no errors with any of the bids.
Construction Estimate:
The total construction cost for this project was estimated at $ 164,000.00 and prepared by Dale Buckingham Architects, LLC. The low bid at $140,522.00 (Base + Alternate 2 + Alternate 3) is 14.4% lower than the Architects’ estimate.
Budget:
Monies for this project have been budgeted from Building Maintenance (50370-73-441-40-44310) in the amount of $100,000.00. Additional funds ($40,522) will be transferred from Maintenance Equipment (503-70-73-441-40-44320).
Contractor’s Review:
Michaels Construction has no apparent problem with their bid. Bid tabulation is attached.
|