Council Consideration for the Acceptance of Public Improvements for Collins Heights Lift Station Capacity Upgrade Project, Installed by North Star Energy and Construction, LLC, in the Amount of $598,509.90. |
BACKGROUND: |
This project upgraded the wet well capacity of the Collins Heights Lift Station located at 4520 University Road.
|
ACTUAL COST VS. BUDGET: |
There were three (3) change orders associated with this project that decreased the contract by $51,209.35 from the original contract amount of $649,719.25.
Change Order | Description | Contract Days Added | Force Account Amount | Contract Amount | 1 | Bed Rock Excavation for Lift Station Pit | 0 | $591.00 | $0.00 | 2 | Replacement of unstable soil around MH #1 and Weather Days | 23 | $685.65 | $0.00 | 3 | Final Quantity Adjustment | 0 | $0.00 | -$51,209.35 | | Total | 23 | $1,276.65 | -$51,209.35 |
|
SUGGESTED MOTION: |
I Move for Approval of the Acceptance of Public Improvements for 12UT06 Collins Heights Lift Station Capacity Upgrade Project, Installed by North Star Energy and Construction, LLC in the Amount of $598,509.90.
|