TIC, The Industrial Company Wyoming, Inc. (TIC) has completed the work for the Gillette Madison Pipeline Project Contract No. 3 In-Town Piping. This work consisted of furnishing and installing approximately 7 miles of 24, 30, and 36-inch diameter PVC water main between Westover and the Southern Drive Tank.
The original bid price to perform this work was $15,090,944.00.
The final contract amount when considering all change orders is $15,328,491.81.
During the October 21, 2013 Council Meeting, the City of Gillette approved a Change Order with TIC as part of this project in the amount of $700,000.00 to resolve a claim associated with the Horizontal Directional Drilling (HDD) work along Westover Rd.
A copy of TIC's Change Order Summary, Final Payment Application and other Close-Out Documents are attached for your information.
City Staff recommends Council acceptance of this project. City Staff also recommends commencement of the 41-day advertisement period starting on Friday, July 18, 2014. Final payment to the Contractor will be made after the 41-day advertisement period is complete, or around August 29, 2014. |