DATE:
|
8/19/2014 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for the WWTF UV Disinfection Building Roof Replacement Project, Installed by New Horizons Alternative Energy Solutions, Inc., in the Amount of $50,820.00. |
BACKGROUND: |
This project consisted of replacing an existing failed single-ply membrane roof on the WWTF UV Disinfection Building. The roof was replaced with a Spray Polyurethane Foam (SPF) Roof system.
|
ACTUAL COST VS. BUDGET: |
There were two (2) change orders associated with this project that decreased the contract by $2,000.00 from the original contract amount of $52,820.00.
Change Order | Description | Contract Days Added | Force Account Amount | Contract Amount | 1 | Additional Spray Foam Insulation around Roof Drains | 0 | $3,000.00 | $0.00 | 2 | Final Quantity Adjustment | 0 | $0.00 | -$2,000.00 | | Total | 0 | $3,000.00 | $-2,000.00 |
|
SUGGESTED MOTION: |
I Move for Approval of the Acceptance of Public Improvements for the WWTF UV Disinfection Building Roof Replacement Project, Installed by New Horizons Alternative Energy Solutions, Inc., in the Amount of $50,820.00
|
STAFF REFERENCE: |
Kendall Glover, Utilities Director |
|
|