Council Consideration for the Acceptance of Public Improvements for the 2013 Sanitary Sewer Main Replacement Project, Installed by North Star Energy and Construction, LLC, in the Amount of $1,780,094.39 (1% Project).
BACKGROUND:
This project consisted of installing 4874 LF of new 8" PVC Sanitary Sewer Mains, in the alley between Rockpile and Richards from 4th to 8th, main in Richards from 9th to 11th, main in the alley between Warren and Ross from 4th to 7th, main in the alley between 11th and 12th from Ross to Dalbey, main in Rohan from 9th to 10th, and main in the alley between Osborne and Brooks from 4th to 6th.  Included also was the rehabilitation of the existing pavement and repair of failed concrete curb and gutter, driveways and valley gutters in the areas of the Sanitary Sewer Main Replacement.
ACTUAL COST VS. BUDGET:
There were four (4) change orders associated with this project that decreased the contract by $88,444.65 from the original contract amount of $1,868,539.04.

 

Change Order

Description

Contract Days Added

Force Account Amount

Contract Amount

1

Concrete step removal and replacement at 1007 Richards, exploratory excavation at 1003 Richards, extend sanitary sewer service at 310 11th Street, remove existing water meter pits that conflicted with proposed sanitary sewer service lines at 309 9th Street, 903 Richards, 907 Richards, 909 Richards, and removal of underground concrete so connection could be made to existing sanitary sewer main at 10th and Rohan.

4

$4,029.00

$0.00

2

Additional driveway replacement in Richards/Rockpile alley between 7th and 8th, re-grading in alleys for grade improvements and driveway tie-in, gas line conflicts delaying work in Warren/Ross alley between 6th and 7th, and gas line lowering and repairs delaying work in the Osborne/Brooks alley between 4th and 5th.

7

$0.00

$0.00

3

Additional asphalt pavement replacement on 9th Street adjacent to the Rohan intersection, exploratory excavation and installation of the additional sanitary sewer service at 603 9th Street, additional asphalt pavement replacement on Dalbey Avenue between 11th and 12Th , Ross Avenue within the intersection of 12th, and additional asphalt pavement replacement on 5th Street between Brooks and Osborne.

7

$2,006.50

$0.00

4

Final Quantity Adjustment

0

$0.00

-$88,444.65

 

Total

18

$6035.50

-$88,444.65

SUGGESTED MOTION:
I Move for Approval of the Acceptance of Public Improvements for 2013 Sanitary Sewer Main Replacement Project, Installed by North Star Energy and Construction, LLC in the Amount of $1,780,094.39 (1% Project).
STAFF REFERENCE: