Council Consideration of a Bid Award for the Water Tank Rehabilitation (Z1-R4 Southern Drive Tank) to Base Group in the Amount of $379,775.00 (1% Project).
BACKGROUND:
This project consists of blasting and re-painting the interior and exterior of the  Z1-R4 Southern Drive Tank.
ACTUAL COST VS. BUDGET:
The City of Gillette, Purchasing Division opened bids for this project at the City Warehouse on Wednesday, January 28, 2015 at 2:30 PM.

The following table summarizes the bids received and the Engineer's Estimate.

 

BIDDER

TOTAL BID

Base Group

$379,775.00

Norvell Construction, LLC

$517,038.00

BSP of Wyoming

$531,600.00

Western Partitions, Inc.

$616,357.80

Great Basin Industries, LLC

$630,281.00

Wyoming Power Wash

$644,580.00

Classic Protective Coatings, Inc.

$772,300.00

Coblaco Services, Inc.

$922,795.00

Purcell Paintings and Coatings

$1,007,131.00

Engineer’s Estimate

$562,500.00


Bid Irregularities :

The bid submitted by Base Group had a small mathematical error.  On their bid form, they showed the Total of Base Bid to be $379,700.00, while the sum of the products of the estimated quantity of each item and the corresponding unit price actually results in the total of $379,775.00, a difference of $75.00.  We recommend this error be considered minor and informal, and do not recommend rejection.

Construction Estimate:

The total construction cost for this project was estimated at $562,500.00 and was prepared by Morrison-Maierle.  The low bid from Base Group was $379,775.00, approximately 32% lower than the Engineer's Estimate.

Budget:

Monies for this project have been budgeted from the 1% Optional Sales Tax Fund #201-10-05-419-70-47413 in the amount of $800,000.00.

Contractor's Review:

Base Group has no apparent problem with their bid.

Bid Tabulation is attached.
SUGGESTED MOTION:
I Move for Approval of the Bid Award for the Water Tank Rehabilitation (Z1-R4 Southern Drive Tank) to Base Group, in the Amount of $379,775.00.
STAFF REFERENCE:
Kendall Glover, Utilities Director