SUBJECT:
Council Consideration of a Professional Services Agreement for Construction Management Services Associated with the WWTF Aeration Basin and Final Clarifier Painting Project with Morrison-Maierle in the Amount of $27,147.00 (1% Project).
BACKGROUND:
This contract will consist of project oversight and inspection services for the WWTF Aeration Basin and Final Clarifier Painting Project.  This project consists of painting the steel piping in the aeration basins and the steel surfaces of two final clarifiers at the Wastewater Treatment Facility (WWTF).  The aeration basins and final clarifiers have failures of the coating system which will require re-coating.  This work includes the removal of existing paint, re-coating the steel piping for the aeration basins and interior steel surfaces of the final clarifiers including all exposed parts, motor, walkway, and all other appurtenances.
ACTUAL COST VS. BUDGET:
The cost for this construction management professional service contract is $27,147.00 which is 11.9% of the construction cost of $227,600.00.  The contract will be funded from the 1% Optional Sales Tax Fund #201-10-05-419-70-47420 which has $400,000.00 budgeted for this project.
SUGGESTED MOTION:
I move for the Approval of a Professional Services Agreement for Construction Management Services Associated with the WWTF Aeration Basin and Final Clarifier Painting Project with Morrison-Maierle, in the Amount of $27,147.00 (1% Project).
STAFF REFERENCE:
Kendall Glover, Utilities Director