Bids were opened and read aloud on March 17, 2015 at the City of Gillette Purchasing Division. Three (3) bids were received on the Project.
The bid results are as follows:
Bidder | Base Bid | Alternate 1 | Alternate 2 |
| | | |
Powder River Construction, Inc. | $231,752.75 | $39,880.00 | $71,163.75 |
S & S Builders, LLC | $246,386.31 | $42,864.40 | $75,126.40 |
Donkey Creek Construction, Inc. | $254,141.25 | $43,932.00 | $80,153.50 |
The Engineer's Estimate, prepared by Consolidated Engineers, Inc., was in the amount of $217,958.42 for the base bid, $32,079.92 for Alternate 1 and $59,883.94 for Alternate 2.
Alternate 1 consisted of asphalt patching and curb and gutter work on the west end of the Little League Parking Lot at Dalbey Park. Alternate 2 consisted of asphalt patching and installation of valley gutter near the center approach of the Little League Parking Lot at Dalbey Park.
It is recommended that the Base Bid and Alternate 1 Bid be awarded at this time in the amount of $271,632.75. Funds are currently not available to include Alternate 2 in this project. The work associated with Alternate 2 will be included in a future project as funding allows.
Funding for this project has been allocated in the Optional 1% Sales Tax Account 201-10-05-419-40-44331.