DATE:
|
8/4/2015 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for the Water Tank Rehabilitation (Z1-R4 Southern Drive Tank) Project, Installed by BSP of Wyoming, LLC., in the Amount of $479,866.00 (1% Project). |
BACKGROUND: |
This project consists of blasting and re-painting the interior and exterior of the Z1-R4 Southern Drive Tank.
|
ACTUAL COST VS. BUDGET: |
There was one (1) change order associated with this project that decreased the contract by $51,734.00, from the original contract amount of $531,600.00.
Change Order | Description | Contract Days Added | Force Account Amount | Contract Amount | 1 | Final Quantity Adjustment | 0 | $0.00 | -$51,734.00 | | Total | 0 | $0.00 | -$51,734.00 |
|
SUGGESTED MOTION: |
I Move for Approval of the Acceptance of Public Improvements for the Water Tank Rehabilitation (Z1-R4 Southern Drive Tank) Project, Installed by BSP of Wyoming, LLC., in the Amount of $479,866.00 (1% Project).
|
STAFF REFERENCE: |
VIDEO
Kendall Glover, Utilities Director |
|
|