Approval Sheet

CITY OF GILLETTE
201 E. 5th Street
Phone (307)686-5200
CITY OF GILLETTE


www.gillettewy.gov

 
DATE: 8/4/2015 7:00:00 PM
SUBJECT:
Council Consideration for the Acceptance of Public Improvements for the Water Tank Rehabilitation (Z1-R4 Southern Drive Tank) Project, Installed by BSP of Wyoming, LLC., in the Amount of $479,866.00 (1% Project).
BACKGROUND:
This project consists of blasting and re-painting the interior and exterior of the Z1-R4 Southern Drive Tank.
ACTUAL COST VS. BUDGET:
There was one (1) change order associated with this project that decreased the contract by $51,734.00, from the original contract amount of $531,600.00.

 

Change Order

Description

Contract Days Added

Force Account Amount

Contract Amount

1

Final Quantity Adjustment

0

$0.00

-$51,734.00

 

Total

0

$0.00

-$51,734.00


SUGGESTED MOTION:
I Move for Approval of the Acceptance of Public Improvements for the Water Tank Rehabilitation (Z1-R4 Southern Drive Tank) Project, Installed by BSP of Wyoming, LLC., in the Amount of $479,866.00 (1% Project).
STAFF REFERENCE:
VIDEO
Kendall Glover, Utilities Director
ATTACHMENTS:
Click to download
Affidavit on Behalf of Contractor
Warranty Agreement