DATE:
|
8/4/2015 7:00:00 PM |
SUBJECT: |
Council Consideration of the Professional Services Agreement for Construction Management Services Associated with the 3rd Street Plaza Project, with HDR Engineering, Inc., in the Amount of $97,800.00 (1% Project and Wyoming Business Council - Business Ready Community Grant). |
BACKGROUND: |
The 3rd Street Plaza Project will consist of the full reconstruction of 3rd Street from South Gillette Avenue to Kendrick Avenue. The reconstruction will provide a convertible street/plaza area to host special events and will enhance the public use of the downtown district.
The reconstruction will include widened sidewalk areas, enhanced landscape/streetscape features, catenary street lighting, special sidewalk lighting, and continuations of the Gillette Avenue design theme.
The project time included 55 working days to Final Completion.
|
ACTUAL COST VS. BUDGET: |
Powder River Construction has been awarded the project with a reduced scope of work in the amount of $909,786.90.
The proposed construction administration cost is $97,800.00. This equates to 10.7% of the construction cost, or approximately $1,778 per day. These fees include nonstandard services such as special electrical and structural review in the amount of $3,350 and landscaping inspections in the amount of $6,160. The estimate also includes $6,500 for materials testing and $5,280 for surveying.
|
SUGGESTED MOTION: |
I Move for Approval of a Professional Services Agreement for the Construction Management Services Associated with the 3rd Street Plaza Project, with HDR Engineering, Inc. in the Amount of $97,800. (1% Project and Wyoming Business Council - Business Ready Community Grant)
|
STAFF REFERENCE: |
Dustin Hamilton, P.E., Development Services Director |
|
|