The project consists of the extension of Boxelder Road from Burma Avenue west to Skyline Drive (Hwy 50). The roadway section will be 3 lanes with curb and gutter on the north side, a detached sidewalk on the north side, and a 10' detached pathway on the south side. Future conversion to a 5 lane section would occur by widening the pavement and installing curb and gutter on the south side of the proposed project. Storm sewer, water main, and sanitary sewer main will also be included in the project. The overall length of the Boxelder Road Extension, Phase III is approximately 2,365 feet.
Dowl will be providing Project Management, Administration, Field Observation, Construction Verification Surveying, Material Testing, and Post Construction Services for the Boxelder Road Extension, Phase III project. This project is estimated to take 135 working days with completion in October 2016. A winter shut down is scheduled on this project after grading and utility work is complete this calendar year.
The proposed construction contract award is in the amount of $2,640,972.04. The proposed CM fee equates to 8.6% of the construction contract amount or $1,687 per day of construction.
|