DATE: 10/6/2015 7:00:00 PM
SUBJECT:
Council Consideration for the Acceptance of Public Improvements for the Swanson Substation Foundations Project as Completed by Mining Electrical Services, LLC, in the Amount of $60,769.80.
BACKGROUND:
The scope of this project covers the installation of the concrete foundations and transformer oil containment for the new Swanson Substation.
ACTUAL COST VS. BUDGET:
The engineering estimate for this project was $70,000.00.  This project was completed at the original contract amount of $60,769.80.
SUGGESTED MOTION:
I Move for Approval of the Acceptance of Public Improvements for the Swanson Substation Foundations Project, as completed by Mining Electrical Services, LLC, in the Amount of $60,769.80.
STAFF REFERENCE:
Kendall Glover, Utilities Director