SUBJECT:
Council Consideration for the Acceptance of Public Improvements for the Wastewater Treatment Facility (WWTF) Aeration Basin and Final Clarifier Painting Project, Installed by Carr Coatings, LLC, in the Amount of $197,124.25 (1% Project).
BACKGROUND:
This project consisted of painting the steel piping in the Aeration Basins and the steel surfaces of two Final Clarifiers at the WWTF.  The Aeration Basins and Final Clarifiers had failures of the coating system which required re-coating.  This work included the removal of existing paint, re-coating the steel piping for the Aeration Basins and interior steel surfaces of the Final Clarifiers, including all exposed parts, motor, walkway, and all other appurtenances.
ACTUAL COST VS. BUDGET:
There was one (1) change order associated with this project that decreased the contract by $30,475.75, from the original contract amount of $227,600.00.

 

Change Order

Description

Contract Days Added

Force Account Amount

Contract Amount

1

Final Quantity Adjustment

0

$0.00

-$30,475.75

 

Total

0

$0.00

-$30,475.75

SUGGESTED MOTION:
I Move for Approval of the Acceptance of Public Improvements for the Wastewater Treatment Facility (WWTF) Aeration Basin and Final Clarifier Painting Project, Installed by Carr Coatings LLC, in the Amount of $197,124.25 (1% Project).