SUBJECT:
Council Consideration of a Bid Award for the 2015 Water Main Replacement to Powder River Construction, Inc., in the Amount of $1,877,786.35 (1% Project).
BACKGROUND:
This project consists of installing approximately 3800 LF of water main within Rose Creek Drive from Foxhills Avenue to Rodeo Street, Cabin Drive from Rose Creek Drive to Harder Drive, Cabin Court, and Morningside Drive from Prairieview Drive to Circle Drive.
ACTUAL COST VS. BUDGET:
The City of Gillette, Purchasing Division, opened bids for this project at the City Warehouse on Wednesday, March 2, 2016, at 2:30 P.M..

The following table summarizes the bids received and the Engineer's Estimate.

 

BIDDER

TOTAL BID

Powder River Construction, Inc.

$1,877,786.35

DRM, Inc.

$1,894,849.25

Earth Work Solutions

$2,003,610.28

Simon Contractors

$2,078,073.00

Hot Iron, Inc.

$2,472,267.72

Mountain View Building, Inc.

$2,649,943.00

EDK Engineering and Construction

$3,218,094.60

Engineer’s Estimate

$2,200,030.00


BID IRREGULARITIES:

There were no errors with any of the bids.

CONSTRUCTION ESTIMATE:

The total construction cost for this project was estimated at $2,200,030.00 and was prepared by Kadrmas, Lee & Jackson.  The low bid from Powder River Construction, Inc., was $1,877,786.35, approximately 14.6% lower than the Engineer's Estimate.

BUDGET:

Monies for this project have been budgeted from the 1% Optional Sales Tax Fund 201-10-05-419-70-47410 in the amount of $3,000,000.00.

CONTRACTOR'S REVIEW:

Powder River Construction, Inc., has no apparent problem with their bid.

Bid Tabulation is attached.
SUGGESTED MOTION:
I Move for Approval of the Bid Award for the 2015 Water Main Replacement Project to Powder River Construction, Inc., in the Amount of $1,877,786.35 (1% Project).
STAFF REFERENCE:
MAP/VIDEO
Kendall Glover, Utilities Director