This project consists of reconstruction of North Osborne Avenue, mill and overlay of Lincoln and Laramie Streets, patch repairs on Brooks Avenue, cement treated base and overlay of EZ Street, and replacement of existing water valves and fitting, hydrant replacements, and selected storm drain repairs.
Bid Opening
Two bids were received, opened, and read aloud by the City of Gillette Purchasing Division at 2:00 PM on March 22, 2016. The bid results were as follows:
CONTRACTOR | BID AMOUNT |
Simon Contractors | $958,362.85 |
Powder River Construction | $1,170,560.65 |
Engineer's Estimate | $1,098,253.00 |
No irregularities were discovered in the review of the bids.
The contractor has 70 working days to achieve substantial completion with an additional 10 working days to achieve final completion.