Approval Sheet

CITY OF GILLETTE
201 E. 5th Street
Phone (307)686-5200
CITY OF GILLETTE


www.gillettewy.gov

 
DATE: 4/5/2016 7:00:00 PM
SUBJECT:
Council Consideration of a Professional Services Agreement for Construction Management Services Associated with the Concrete Apron Repairs Z1-R4 Tank and Driveway Repairs Z1-R5, with Morrison-Maierle, in the Amount of $32,364.00 (1% Project).
BACKGROUND:
This contract will consist of project oversight and inspection services for the Concrete Apron Repairs Z1-R4 Tank and Driveway Repairs Z1-R5 Project.  This project will replace all of the failing concrete apron around the Z1-R4 (Southern Drive Tank) and install new driveway from Doud Drive to Z1-R5 (Hidden Valley Tank).
ACTUAL COST VS. BUDGET:
The cost for this construction management professional service contract is $32,364.00 which is 11.1% of the construction cost of $290,485.70.  The contract will be funded from the 1% Optional Sales Tax Fund #201-10-05-419-70-47413, which has $425,000.00 budgeted for this project.
SUGGESTED MOTION:
I Move for the Approval of a Professional Services Agreement for Construction Management Services Associated with the Concrete Apron Repairs Z1-R4 Tank and Driveway Repairs Z1-R5, with Morrison-Maierle, in the Amount of $32,364.00 (1% Project).
STAFF REFERENCE:
Kendall Glover, Utilities Director
ATTACHMENTS:
Click to download
Agreement
Exhibit A
Exhibit B
Exhibit C
Exhibit D
Exhibit E
Exhibit G
Exhibit H
Exhibit I
Exhibit K