Council Consideration for the Acceptance of Public Improvements for the Concrete Apron Repairs Z1-R4 Tank and Driveway Repairs Z1-R5 Project, Installed by S&S Builders, LLC, in the Amount of $283,744.75 (1% Project). |
BACKGROUND: |
This project consisted of replacing all of the failed concrete apron around the Z1-R4 (Southern Drive Tank) and installing a new driveway from Doud Drive to Z1-R5 (Hidden Valley Tank).
|
ACTUAL COST VS. BUDGET: |
There were two (2) change orders associated with this project that decreased the contract by $6,740.95, from the original contract amount of $290,485.70.
Change Order | Description | Contract Days Added | Force Account Amount | Contract Amount | 1 | Removal of Guard Rail, Installation of Drain Line | 1 | $1,209.50 | $0.00 | 2 | Final Quantity Adjustment, Conversion of Asphalt to Concrete Pavement | 3 | $0.00 | -$6,740.95 | | Total | 4 | $1,209.50 | -$6,740.95 |
|
SUGGESTED MOTION: |
I Move for Approval of the Acceptance of Public Improvements for the Concrete Apron Repairs Z1-R4 Tank and Driveway Repairs Z1-R5 Project, Installed by S&S Builders, LLC, in the Amount of $283,744.75 (1% Project).
|
STAFF REFERENCE: |
VIDEO
Kendall Glover, Utilities Director |
|
|