DATE:
|
10/4/2016 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for the 2015 Water Main Replacement Project, Installed by Powder River Construction, Inc., in the Amount of $1,475,773.30 (1% Project). |
BACKGROUND: |
This project consisted of installing 2760 LF of 8" PVC water main within Rose Creek Drive from Foxhill Avenue to Rodeo Street and 517 LF of 6" PVC water main within Morningside Drive from Prairieview Drive to Circle Drive.
|
ACTUAL COST VS. BUDGET: |
There were five (5) change orders associated with this project that decreased the contract by $402,013.05, from the original contract amount of $1,877,786.35.
Change Order | Description | Contract Days Added | Force Account Amount | Contract Amount | 1 | Weather Days | 7 | $0.00 | $0.00 | 2 | Weather Days | 3 | $0.00 | $0.00 | 3 | Video of Sanitary Sewer Service and Edge Drain Perforated Pipe | 3 | $0.00 | $2,038.05 | 4 | Additional Asphalt Patch at Cabin and Harder | 1 | $0.00 | $7,507.50 | 5 | Final Quantity Adjustment | 0 | $0.00 | -$411,558.60 | | Total | 14 | $0.00 | -$402,013.05 |
|
SUGGESTED MOTION: |
I Move for Approval of the Acceptance of Public Improvements for the 2015 Water Main Replacement Project, Installed by Powder River Construction, Inc., in the Amount of $1,475,773.30 (1% Project).
|
STAFF REFERENCE: |
MAP/VIDEO
Kendall Glover, Utilities Director |
|
|