Approval Sheet

CITY OF GILLETTE
201 E. 5th Street
Phone (307)686-5200
CITY OF GILLETTE


www.gillettewy.gov

 
DATE: 2/7/2017 7:00:00 PM
SUBJECT:
Council Consideration for the Acceptance of Public Improvements for the Gillette Madison Pipeline Project, Contract 6, Installed by COP Wyoming, in the Amount of $1,928,260.79.  
BACKGROUND:

This project consisted of the furnishing and installing of a new 300,000 gallon welded steel water storage tank and associated piping and appurtenances.  The project also included inlet/outlet piping, overflow piping, drain piping, piping connections to the existing Gillette Madison Pipeline, tank appurtenances, electrical, instrumentation, controls, overflow discharge structures, general site work, site restoration, and all other incidental items required to complete a functioning system.

ACTUAL COST VS. BUDGET:

The original contract amount for this project was $1,924,432.00.  There were two change orders for a net added cost to the project of $3,828.79 (0.2% increase).  Below is a summary of these change orders:

 

Change Order

Description

Contract
Time

Change Order
Amount

01

Add insulation board between 30" Madison pipeline and new culvert

0

$2,800.00

02

Add intrusion alarm on roof hatch

0

$1,028.79

Total

+29

$ 3,828.79

 

This project was eligible for 67% reimbursement from the Wyoming Water Development Commission through the 67% grant and the 33% loan we have with them.  The remaining 33% was paid for by CAP Tax funds.

Budget Account No.  301-70-72-441-70-47411

Project No. 07EN58

SUGGESTED MOTION:
I Move for Approval for the Acceptance of Public Improvements for the Gillette Madison Pipeline Project, Contract 6, Installed by COP Wyoming, in the Amount of $1,928,260.79.
STAFF REFERENCE:
MAP - Kendall Glover, Utilities Director
ATTACHMENTS:
Click to download
Certificate of Final Completion
Affidavit on Behalf of Contractor
Warranty