DATE: 2/7/2017 7:00:00 PM
SUBJECT:
Council Consideration for the Acceptance of Public Improvements for the Gillette Regional Water Supply Project Phase I District Extensions, Installed by Redpoint Contracting, in the Amount of $6,156,852.38. 
BACKGROUND:
This project is the first phase of a series of projects to provide water to water districts as part of the Gillette Regional Water Supply project.  This project extended water to Cook Road, Bennor Estates, Overbrook, Rafter D, Spring Hill Ranch, Southfork, and Antelope Valley.  To facilitate these connections, this project consisted of the installation of approximately 54,000 lineal feet of 12" and 8" PVC water main, two pump stations, and seven control buildings.  
 
The Antelope Valley connection was made by connecting to the new pipeline at the corner of Patty Ave. and Schoonover Rd. and running a new 12" PVC pipeline to the Antelope Valley water tank.  Spring Hill Ranch is connected to the City of Gillette Distribution system in Hidden Valley Rd. with a new 8" PVC pipeline that will connect to their distribution system near their well site.  The remaining five water districts are connected to a 12" PVC pipeline that begins at the Z1R5 tank in the Doud Ranch Subdivision.  This pipeline was installed in Rock Rd., Brahma St., Roany Rd., and along Force Rd.  Connections to this pipeline for each water district are made with 8" PVC pipelines.  All seven water district connections include a control building that houses a water meter, backflow preventer, supervisory control and data acquisition (SCADA) equipment, and all other necessary valves, piping, and equipment to provide water to these districts.

 

Three separate payment bond claims were filed by subcontractors in the course of closing out the project.  As such, a consent of surety, affidavit on behalf of contractor, lien waivers (conditional and unconditional) are provided.  To the best of the knowledge of staff, one claim has been resolved, and two have outstanding disagreements and are being handled by legal proceedings between the parties.

 

The contractor is providing an additional 2 year warranty for the Antelope Valley Pump Station Yaskawa Variable Frequency Drives (VFDs), 50 horsepower Baldor Motors, and CR-120 Grunfos Pumps due to a failed pump test at the specified conditions.  In order to achieve the specified flow and pressure, the motors have to be run at 62 hertz rather than the specified 60 hz.  Each manufacturer has provided written assurance that their equipment can safely operate at these conditions without affecting the service life.  Additionally, the contractor paid for the Engineer's time in responding to this failed test through a pay item deduction in the amount of $2,240.00.

ACTUAL COST VS. BUDGET:

The budget for this project was $9,600,000.00, which includes engineering, land acquisition, and construction phase inspection services.  The Engineer's estimate for construction at the time of bidding was $7,045,260.00 and the following bids amounts were received.  

 

Bidder

Bid Price

Redpoint Contracting

$5,580,150.00

DRM

$6,164,366.75

Mountain View Building

$6,422,145.00

Western Municipal Construction

$6,451,460.00*

SJ Louis

$8,047,275.00*

*Bid value was corrected due to numerical errors discovered by DOWL during bid review.

 

The original contract amount for this project was $5,580,150.00.  There were eleven change orders for a net added cost to the project of $576,702.38 (10.3% increase).  Below is a summary of these change orders:

 

Change Order

Description

Contract
Time

Change Order
Amount

01

Allowance of pre-cast buildings in place of tilt-up design

0

$(9,427.00)

02

Additional HDD for County designated driveways along Force Rd

0

$56,212.00

03

Modifications to the bore under Force Rd due to lack of room in easement

0

$1,161.00

04

Modifications to the electrical feed and transfer switches and the addition of a double door in the Gillette West Pump Station, Antelope Valley Pump Station, and Spring Hill Ranch Pump Station.

0

$6,611.00

05

Address cost and schedule impact associated with compliance with the Campbell County General License Permit for Force Rd.

70

$621,000.00

06

Address impacts to contractor's work due to the damaging of an unmarked 2" plastic water service line in the Southfork Water District along Brahma St.

0

$7,653.00

07

Deduct expenses for re-testing of backfill materials from amount due to contractor.

0

$(7,635.00)

08

Southfork, Overbrook, and Antelope Valley tie-in and location modifications.

0

$(188.00)

09

Modifications to building electrical and plumbing.

13

$21,423.00

10

Antelope Valley Control Building elevation adjustment, Construct access road to Antelope Valley Pump Station, Antelope Valley Pump Station electrical modifications, contract time adjustment for bid item overruns, modify Overbrook tie-in.

23

$31,943.78*

11

Final Quantity Adjustments

0

$(151,483.40)

Total

+106

$576,702.38

*Reimbursed by DOWL through deduction in professional services contract due to error in design.

 

Substantial completion contract time was overrun by 29 days, resulting in $52,200.00 in liquidated damages for substantial completion charged to the contractor. Additionally, final completion contract time was overrun by 49 days, resulting in $63,700.00 in liquidated damages charged for final completion.  In total, $115,900.00 in liquidated damages was deducted from contractor payments.

 

Budget Account No.  301-70-72-441-70-47414
Project No. 12UT05
SUGGESTED MOTION:
I Move to Approve the Acceptance of Public Improvements for the Gillette Regional Water Supply Project Phase I District Extensions, Installed by Redpoint Contracting, in the Amount of $6,156,852.38.
STAFF REFERENCE:
MAP - Kendall Glover, Utilities Director
ATTACHMENTS:
Click to download
Warranty
Extended Warranty
Affidavit on Behalf of Contractor
Consent of Surety
Conditional Lien Waivers
Unconditional Lien Waivers
Certificate of Final Completion
DOWL Acceptance Recommendation