Bids were opened and read aloud on February 22, 2017 at the City of Gillette Purchasing Division. Seven (7) bids were received on the project.
The bid results are as follows:
Bidders Bid Amount (Base + Alt. 1 and 2)
Van Ewing Construction $85,631.94
Hladky Construction $86,696.00
Mountain View Construction $87.586.00
DRM $94,394.25
S & S Builders, LLC $97,145.00
GW Construction $105,498.10
PRC $109,140.00
The Engineer's Estimate, prepared by City of Gillette Staff was in the amount of $118,975.00.
Funding for this project has been allocated in the Optional 1% Sales Tax account 201-10-05-419-90-49010, as well as a private donation from Cloud Peak Energy and Supported in part by a grant from the Wyoming Cultural Trust Fund, a program of the Department of State Parks and Cultural Resources.
It is recommended that the Base bid and the two alternate bids in the amount of $85,631.94 be awarded at this time. |