Approval Sheet

CITY OF GILLETTE
201 E. 5th Street
Phone (307)686-5200
CITY OF GILLETTE


www.gillettewy.gov

 
DATE: 3/7/2017 7:00:00 PM
SUBJECT:
Council Consideration of a Bid Award for the 2016 Sanitary Sewer Main Replacement to Hot Iron, Inc., in the Amount of 2,202,470.44 (1% Project).
BACKGROUND:

This project consists of installing approximately 5040 LF of sanitary sewer main replacement in the following areas:

 

1.  The alley between Brooks Avenue and Emerson Avenue from 6th Street to 8th Street.

2.  The alley between 4J Road and Rockpile Avenue from 4th Street to 6th Street.

3.  Hog Eye Drive from Jack Plane Lane to Wagonhammer Lane.

4.  Juniper Lane from Wagonhammer Lane to S. Gillette Avenue.

5.  Redwood Street from S. Gillette Avenue to S. Emerson Avenue.

6.  Birch Street from Sunflower Park to Redwood Street.

7.  S. Hwy. 59 from Sioux Avenue to Sinclair Street.

8.  Shoshone Avenue from Clemence Avenue to Dakota Street.

 

ACTUAL COST VS. BUDGET:

The City of Gillette Purchasing Division opened bids for this project at the City Warehouse on Wednesday, February 15, 2017, at 2:30 P.M..

 

The following table summarizes the bids received and the Engineer's Estimate.

 

BIDDER

TOTAL BID

Hot Iron, Inc.

$2,202,470.44

DRM, Inc.

$2,101,428.00 + 5%= $2,206,499.40

COP Wyoming, LLC

$2,493,902.00

Simon Contractors

$2,529,210.00

Powder River Construction

$2,543,502.50

Mountain View Builders

$3,094,821.00

Engineer’s Estimate

$2,560,690.00

 

BID IRREGULARITIES:

 

The six bidders on the project were Hot Iron, Inc., DRM, Inc., COP Wyoming, LLC, Simon Contractors, Powder River Construction, Inc., and Mountain View Builders.  All bids were submitted on time and had the required Bid Bond.  All bids included a Residency Certificate except for DRM, Inc.  Since DRM, Inc. did not provide the required Certificate of Residency with their bid as required by paragraph 12.04 of the Instructions to Bidders, 5% was added to their total bid price in our evaluation of the bids.

Based on the above evaluation, we recommend that the City Council award the project to Hot Iron, Inc. at the bid amount of $2,202,470.44.

 

CONSTRUCTION ESTIMATE:

 

The total construction cost for this project was estimated at $2,560,690.00 and was prepared by HDR Engineering.  The low bid from Hot Iron, Inc. was 2,202,470.44, approximately 16.2 % lower than the Engineer's Estimate.

 

BUDGET:

 

Monies for this project have been budgeted from the 1% Optional Sales Tax Fund #201-10-05-419-70-47420 in the amount of $3,200,000.00.

 

CONTRACTOR'S REVIEW:

 

Hot Iron, Inc. has no apparent problem with their bid.

 

Bid Tabulation is attached.

SUGGESTED MOTION:
I Move for Approval of the Bid Award for the 2016 Sanitary Sewer Main Replacement Project to Hot Iron, Inc., in the Amount of $2,202,470.44 (1% Project).
STAFF REFERENCE:

MAP/VIDEO - Kendall Glover, Utilities Director

ATTACHMENTS:
Click to download
Bid Tabulation