The City of Gillette, Purchasing Division, opened bids for this project at the City Warehouse on Wednesday, February 14, 2018 at 3:00 P.M.
The following table summarizes the bids received and the Engineer's Estimate.
BIDDER
|
TOTAL BID
|
COP Wyoming, LLC
|
$1,294,693.00
|
Hot Iron, Inc.
|
$1,300,691.74
|
Engineer’s Estimate
|
$1,449,650.00
|
BID IRREGULARITIES
The two bidders on the project were Hot Iron, Inc., and COP Wyoming LLC. Both bids were submitted on time and had the required Bid Bond. Both bids included a Residency Certificate. No irregularities were found that would justify rejection of a bid.
Based on the above evaluation, we recommend that the City of Gillette award the project to COP Wyoming, LLC at the bid amount of $1,294,693.00.
CONSTRUCTION ESTIMATE
The total construction cost for this project was estimated at $1,449,650.00 and was prepared by HDR Engineering. The low bid from COP Wyoming, LLC., was 1,294,693.00, approximately 10.7% or $154,957.00 lower than the Engineer's Estimate.
BUDGET
Monies for this project have been budgeted from the 1% Optional Sales Tax Fund #201-10-05-419-70-47410 in the amount of $3,600,000.00.
CONTRACTOR'S REVIEW
COP Wyoming, LLC., has no apparent problems with their bid.