Approval Sheet

CITY OF GILLETTE
201 E. 5th Street
Phone (307)686-5200
CITY OF GILLETTE


www.gillettewy.gov

 
DATE: 3/20/2018 7:00:00 PM
SUBJECT:
Council Consideration of a Bid Award for the Madison Water Load-out Facility and Pine Ridge Tank Drain Project to Hot Iron, Inc., in the Amount of $258,230.57.
BACKGROUND:
This project will build a new public water load out facility at the existing Madison Pump Station and install a new overflow drain line from the Pine Ridge Tank, underground to the outlet discharge head-works North East of the tank.
ACTUAL COST VS. BUDGET:

The City of Gillette, Purchasing Division, opened bids for this project at the City Warehouse on Wednesday, March 7, 2018 at 3:00 P.M.

The following table summarizes the bids received and the Engineer's Estimate.

BIDDER

TOTAL BID

Hot Iron, Inc.

$258,230.57

Hladky Construction, Inc.

$286,881.20

Engineer’s Estimate

$287,726.00

BID IRREGULARITIES

The two bidders on the project were Hot Iron, Inc., and Hladky Construction, Inc.  All bids received appeared to meet all requirements.  All forms were signed, sealed, used City of Gillette forms, and had bid bonds for the correct amounts.

Both contractors submitted a Wyoming Residency Certificate.  Thus the 5% Wyoming Preference Act of 1971, W.S. 16-6-201 did not cause a change in the lowest bidder.

There were minor mathematical errors associated with Hladky Construction's bid.  Two of the unit prices shown on the received bid, when multiplied by the bid quantity did not match total shown on Hladky Construction's bid form.  In accordance with Section 00200 14.01(C), discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices.   Correcting the bid in favor of the unit prices, Hladky Construction's bid increased by $0.66.  This did not change the order of the bidders.  Morrison-Maierle considers both bids to be responsive bids.

CONSTRUCTION ESTIMATE

The total construction cost for this project was estimated at $287,726.00 as was prepared by Morrison-Maierle.  The low bid from Hot Iron, Inc., was $258,230.57, approximately 10.3% or $29,495.43 lower than the Engineer's Estimate.

BUDGET

Monies for this project have been budgeted from the Madison Water Fund #301-70-72-441-70-47414 in the amount of $400,000.00.

CONTRACTOR'S REVIEW

Hot Iron, Inc., had no apparent problems with their bid.

Bid Tabulation is attached.

SUGGESTED MOTION:
I move for Approval of a Bid Award for the Madison Water Load-out Facility and Pine Ridge Tank Drain Project to Hot Iron, Inc., in the Amount of $258,230.57.
STAFF REFERENCE:
MAP - Heath VonEye, P.E., Development Services Director
ATTACHMENTS:
Click to download
Bid Tabulation
Map