Bids were opened and read aloud on Wednesday, March 14, 2018, by the City of Gillette Purchasing Division. Only one bid was received.
Simon Contractors' bid was in the amount of $78,822.00.
The remaining balance for the Large Asphalt Patch Project is $60,188.81. Based on Simon's bid, there is an $18,653.19 shortfall in the remaining budget.
In order to complete the Spring 2018 work as scoped, $18,653.19 plus $2,000 to $3,000 for materials testing will be used from other projects' savings in the 1% Optional Sales Tax fund (the unused portion of the PMS 2018 Schedule A funds, for example).
No errors were found in the bid package. The City of Gillette Engineering Division performed the design and will provide the construction oversight for this work. Materials Testing will be performed by a sub-consultant.
The funding for this project has been allocated from the 1% Optional Sales Tax Account 201-10-05-419-40-44331. |