This project includes replacing approximately 1000 LF of 8-inch sanitary sewer main between five different locations, the installation of approximately 550 LF of new 12-inch water main and installing additional fire hydrants. Two (2) City water system connection points will also be completed and the replacement of 500 LF of sanitary sewer service lines and replacement of six (6) existing sanitary sewer manholes.
Construction Management services for the 35 working day plus the ten (10) working days from issuance of the Certificate of Substantial Completion to Final Completion and will include the pre-construction meeting with the City of Gillette and Hot Iron, Inc., review of drawings, schedules, submittals, and a Resident Project Representative (RPR) for inspection services, materials testing, survey, construction staking, progress meetings during construction, construction reports, monthly and final contractor pay requests, full time project inspection, project engineer's services and Drawings of Construction Record.
The cost breakdown for the Construction Management is as follows:
Full Time Inspection $53,281.00
Construction Staking/Survey $11,115.00
Materials Testing $10,670.00
Post Construction Services/Closeout $4,574.00
The proposed fee equates to $1770.00 per day of construction or 9% of the construction bid amount. |