DATE:
|
10/16/2018 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for the 4J Pathway Repairs Project, Installed by Wyoming Earthmoving Corporation (WEC), in the Amount of $154,203.41 (1% Project). |
BACKGROUND: |
This project (18EN18) consisted of re-grading and installing 840 SY of Asphaltic Pavement on the 4J Pathway in the area between Campbell County Public Health South Parking Lot Entrance South to W. Walnut Street (see attached map). |
ACTUAL COST VS. BUDGET: |
There were two (2) change orders associated with this project that increased the contract by $4,188.81 from the original amount of $150,014.60.
Change Order
|
Description
|
Contract Days Added
|
Force Account Amount
|
Contract Amount
|
1
|
Additional Work: Dewatered area and relocated sprinkler piping
|
7
|
$4,750.81
|
$0.00
|
2
|
Additional Work: Hauling 109 CY topsoil to site, raised sprinkler control box to grade, adjusted path grades near drainage channel, and perform additional finish grading.
|
0
|
$991.19
|
$4,188.81
|
|
Total
|
7
|
$5,742.00
|
$4,188.81
|
|
SUGGESTED MOTION: |
I move for Approval of the Acceptance of Public Improvements for the 4J Pathway Repairs Project, Installed by Wyoming Earthmoving Corporation (WEC), in the Amount of $154,203.41 (1% Project). |
STAFF REFERENCE: |
VIDEO - Ry Muzzarelli, P.E., Development Services Director |
|
|