DATE:
|
1/2/2019 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for the Buckskin Improvement & Service District (I&SD) Water Connection, Installed by DRM, Inc., in the Amount of $82,602.94. |
BACKGROUND: |
The Buckskin I&SD, located northeast of the intersection of North Gurley Avenue and Kluver Road, experienced a complete well failure in May, 2018. This project provides a new permanent connection to the Gillette Regional Water Supply Project (GRWSP) for the Buckskin I&SD. This project included the installation of a new vault, 6" pipeline, and other appurtenances necessary to provide the new service. |
ACTUAL COST VS. BUDGET: |
The original contract amount for this project was $80,593.90. There was one change order for a net added cost to the project of $2,009.04 (2.5% increase). This change order included a revised fitting for the connection point, a tie in to Buckskin's pump station, a 2' fire hydrant extension, and final quantity adjustments.
This project is not eligible for reimbursement from the WWDC and therefore was paid for with CAP Tax.
Budget Account No. 301-70-72-441-70-47417
Project No. 18UT02 |
SUGGESTED MOTION: |
I Move to Approve the Acceptance of Public Improvements for the Buckskin Improvement & Service District (I&SD) Water Connection, Installed by DRM, Inc., in the Amount of $82,602.94. |
STAFF REFERENCE: |
MAP - Michael H. Cole, P.E., Utilities Director |
|
|