Council Consideration of a Bid Award for the 2018 Sanitary Sewer Main Replacement to Mountain View Building, Inc., in the Amount of $548,628.00 (1% Project).
BACKGROUND:
This project will be replacing an existing sanitary sewer main adjacent to Potter Avenue from University Road to Potter Avenue (approximately 490 LF of 12" PVC).  Included with this project will be some slope stabilization in the area disturbed by construction of the new sanitary sewer main.
ACTUAL COST VS. BUDGET:

The City of Gillette, Purchasing Division, opened bids for this project at the City Warehouse on Thursday, January 31, 2019 at 2:30 P.M..

The following table summarizes the bids received and the Engineer's Estimate.

BIDDER

TOTAL BID

LJS Concrete and Excavation

$758,203.00

Wyoming Earthmoving Corporation

$756,475.94

JR Civil

$741,733.07

Hot Iron, Inc.

$617,866.19

Mountain View Builders

$548,628.00

Engineer’s Estimate

$799,750.00

BID IRREGULARITIES:

The five bidders on the project were LJS Concrete & Excavation, Wyoming Earthmoving Corporation, JR Civil, Hot Iron, Inc., and Mountain View Building, Inc..  All bids were submitted on time and had the required Bid Bond.  All bids included a Residency Certificate and acknowledged Addendum #1.

CONSTRUCTION ESTIMATE:

The total construction cost for this project was estimated at $799,750.00 and was prepared by DOWL.  The low bid from Mountain View was $548,628.00, approximately 31% lower that the Engineer's Estimate.

BUDGET:

Monies for this project have been budgeted from the 1% Optional Sales Tax Fund #201-10-05-419-70-47420 in the amount of $1,600,000.00.

CONTRACTOR'S REVIEW:

Mountain View Builders has no apparent problem with their bid.

Bid Tabulation is attached.


SUGGESTED MOTION:
I move for Approval of a Bid Award for the 2018 Sanitary Sewer Main Replacement Project to Mountain View Building, Inc., in the amount of $548,628.00 (1% Project).
STAFF REFERENCE:
MAP/VIDEO - Ry Muzzarelli, P.E., Development Services Director
ATTACHMENTS:
Click to download
Bid Tabulation
Site Map
Map