Council Consideration of a Professional Services Agreement for Construction Phase Services for the Wastewater Treatment Plant Anaerobic Digester Cleaning and Coating Project with Morrison-Maierle, Inc., in the Amount of $25,376.00.
BACKGROUND:

This project consists of painting the steel surfaces of a 60-ft diameter digester at the Wastewater Treatment Facility.  The digester has failures of the coating system which will require re-coating. This work includes the removal of sludge and cleaning of the digester, removal of the existing paint, re-coating the interior and exterior steel surfaces of the digester including all exposed parts and all other appurtenances.  Three valve replacements are included while the digesters are out of service. Two roof support brackets and a digester lid are also scheduled to be replaced. The project was bid with and additive alternate that adds the cleaning and painting of an additional 60-ft diameter digester as well as replacing four additional roof support brackets, on additional valve, and on additional digester lid.

Morrison-Maierle's services for this project will include review and approval of submittals and shop drawings, site inspection services, progress meetings, and preparation of record drawings.

ACTUAL COST VS. BUDGET:
Funds have been appropriated within the FY 2018/19 Budget from the Sewer Fund, Budget Account 505-70-75-443-30-43210.
SUGGESTED MOTION:
I Move for Approval of a Professional Services Agreement for Construction Phase Services for the Wastewater Treatment Plant Anaerobic Digester Cleaning and Coating Project with Morrison-Maierle, Inc., in the Amount of $25,376.00.