The City of Gillette, Purchasing Division, opened bids for this project at the City Warehouse on Tuesday, March 19, 2019 at 2:30 PM.
The following table summarizes the bids received and the Engineer's Estimate.
BIDDER
|
TOTAL BID
|
Hot Iron, Inc.
|
$1,983,230.95
|
Powder River Construction, Inc.
|
$2,049,741.14
|
Simon Contractors
|
$2,294,572.00
|
DRM, Inc.
|
$2,491,919.35
|
Engineer’s Estimate (KLJ)
|
$2,434,654.00
|
BID IRREGULARITIES
Review of the submitted bids found no formal or informal bid discrepancies and KLJ considers all bidders to be responsive bids.
Based on the above evaluation, KLJ recommend that the City of Gillette award the project to Hot Iron, Inc. at the bid amount of 1,983,230.95.
CONSTRUCTION ESTIMATE
The total construction cost for this project was estimated at $2,434.654.00 and was prepared by KLJ. The low bid received from Hot Iron, Inc. was $1,983,230.95, approximately 18.5% or $451,423.05 lower than the Engineer's Estimate.
BUDGET
Monies for this project have been budgeted from the 1% Optional Sales Tax Fund #210-10-05-419-70-47410 in the amount of $3,400,000.00.
CONTRACTOR'S REVIEW
Hot Iron, Inc. has no apparent problems with their bid.