The City of Gillette, Purchasing Division, opened bids for the project at the City Warehouse on Tuesday, March 26, 2019 at 2:30 P.M..
The following table summarizes the bids received and the Engineer’s Estimate.
Bidder
|
Total Bid
|
Classic Protective Coatings, Inc.
|
$ 889,750.00
|
Engineer’s Estimate
|
$ 670,000.00
|
BID IRREGULARITIES:
The only bidder on the project was Classic Protective Coatings, Inc.. Their bid was submitted on time and had the required Bid Bond and acknowledged Addendum #1 and Addendum #2.
CONSTRUCTION ESTIMATE:
The total construction cost for this project was estimated at $670,000.00 as was prepared by Morrison Maierle. The low bid from Classic Protective Coatings, Inc. was $889,750.00, approximately 32.8% higher than the Engineer’s Estimate.
Budget:
Monies for this project have been budgeted from the 1% Optional Sales Tax Fund #201-10-05-419-70-47413 in the amount of $900,000.00.
Contractor’s Review:
Classic Protective Coatings, Inc. has no apparent problem with their bid.
Bid Tabulation is Attached.
|